1650 Sqft Price Plane Detail
We promise to provide the best structure to your dream house
- 2-D Drawing Floor Plan => Yes
- Structural Drawing => Yes
- 3-D Elevation Drawing => Yes
- Furniture plan => No
- As built Drawing => Yes
- Plum concreting (Brick Bat + Cement Mortar) => Yes
- ATT => Yes
- Plain Cement Concrete (PCC) => Yes
- Reinforced Cement Concrete (RCC) => Yes
- Footing => M-20
- Plinth Beam => M-20
- Column => M-20
- Slab & Beam => M-20
- Brick => Class-1
- Cement- Make => MP Birla, Ultratech, ACC or equivalent
- Steel/Reinforcement => gallant/R.H.L./JINDAL
- Waterproofing Chemical in Concrete
- Internal Plaster => 1:5 mix
- External Plaster (Front & Back Elevation only) => 1:5 mix
- Hall => Vitrified tile (2’x4′)- Basic Market Rate 65 Rs/Sqft
- Kitchen- Flooring => —
- Kitchen- Dadoing/Wall => —
- Kitchen- Plateform => Yes
- Balcony => Vitrified tile (1’x1′)- Basic Market Rate upto 40 Rs/ Sqft
- Toilet- Flooring => Vitrified tile (1’x1′)- Basic Market Rate upto 40 Rs/ Sqft
- Toilet- Dadoing/Wall => Vitrified tile (1’x1′)- Basic Market Rate upto 40 Rs/ Sqft
- Staircase- Tread & Riser => Granite (Any Size)- Basic Market Rate 90 Rs/Sqft
- WC Pipe – UPVC => Supreme/ Astral/surya
- Water Pipe- PVC Pipe => Supreme/ Astral/surya
- Water Closet => Economical Series-Parryware/ JAQUAR,JHONSON, Hindware
- Cistern => Exposed Type
- Wash Basin => Economical SeriesParryware/JAQUAR, Hindware
- Shower Assembly => Economical Series-Parryware/ JAQUAR, Hindware- Mixer
- Wash Basin Pillar Cock => Pillar cock
- Kitchen Sink => Economical Series-Parryware/ Hindware- sink with Mixer
- Bath Tub => No
- Switch Box => ISI Mark
- Switch => Anchor-Roma/ Havells
- Cable for Light & Fan (1 Sqmm) => Polycab, Havels Cable or equivalent
- Cable for Gyser (2 Sqmm) => Polycab, Havels Cable or equivalent
- Cable for AC (4 Sqmm) => Polycab, Havels Cable or equivalent
- Door & Window Frame => Malesian Sakhu, UPVC DOOR
- Main Door => Flush Door
- Door => ISI Mark-Flush Door
- Window => upvc
- Hardware => ISI Mark
- Putty => Birla
- Primer => 1 Coat
- Paint => 2 Coat of Asian- Apex or equivalent,
- Boring work => No
- Water Tank- Overhead Tank => Yes
- Main Gate => Iron gate -upto 100 kg
- Provision for AC-Concealed => No
- Camera => No
- Door Phone => No
- Staircase Railing => MS Railing
- Balcony Railing => MS Railing
- Toilet W/P => Yes
- Balcony W/P => Waterproof camical only
- Terrace W/P => Waterproof camical only
- Laminate/Mica => ISI mark- 0.8 mm thick laminate
- Hardware => ISI Mark
PAYMENT SCHEDULE
- Advance
- After Foundation
- At Slab level Basement
- At Slab level F.F.
- At slab level S.F.
- Brick Work.
- Plaster.
- At Final Level.
- 10% approx estimated cast
- 10% approx estimated cast
- 15% approx estimated cast
- 10% approx estimated cast
- 10% approx estimated cast
- 15% approx estimated cast
- 15% approx estimated cast
- 05% approx estimated cast
- Advance
- After Foundation
- At Slab level Basement
- At Slab level F.F.
- At slab level S.F.
- Brick Work.
- Plaster.
- At Final Level.
- 10% approx estimated cast
- 10% approx estimated cast
- 15% approx estimated cast
- 10% approx estimated cast
- 10% approx estimated cast
- 15% approx estimated cast
- 15% approx estimated cast
- 05% approx estimated cast
- Advance : 10% approx estimated cast
- After Foundation : 10% approx estimated cast
- At Slab level Basement : 15% approx estimated cast
- At Slab level F.F. : 10% approx estimated cast
- At slab level S.F. : 10% approx estimated cast
- Brick Work. : 15% approx estimated cast
- Plaster : 15% approx estimated cast
- At Final Level : 05% approx estimated cast